WWTP FOR LIÊN PHƯƠNG IZ (THƯỜNG TÍN - HÀ NỘI)

Lien Phuong industrial wastewater treatment plant - Thuong Tin district - Hanoi

  • Address: Thuong Tin District - Hanoi

  • Employer: People's Committee of Thuong Tin district

  • Capacity: 500 m3/day and night

On December 2, 2013, the Hanoi People's Committee issued Decision No. 7209/QD-UBND approving the project feasibility study to build a centralized wastewater treatment system in these industrial clusters in Hanoi City in stage 2014-2015. In this plan, Lien Phuong industrial cluster (People's Committee of Thuong Tin district was Employer), would construct and operate of a centralized wastewater treatment system with a capacity of 500 m3 / day with the total capital of 4.75 billion VND. The centralized wastewater treatment system will meet QCVN 40:2011/MONRE standards.
Khang Nguyen Investment and Trading Company Limited is the contractor for construction, supply and installation of waste water treatment system. The system finished in 2016.